Approval record: Sample run
Record resin, shot weight with runner, mold stack height, opening stroke and the injection unit the factory selected. Run overlapping clamp, inject, hold, cool and eject steps. Write the energy meter boundary: press only, or press plus dryer, chiller and robot. Count acceptable parts across the same operating sequence. A dry-cycle brochure time is not an approval record. If inserts are used, attach the location and verification step to this sample-run note.
Site readiness
List footprint, three-phase supply, cooling water GPM/psi, compressed air demand and PLC interface names. Mark foundations, lifting, installation, training and spare parts as included or extra. Destination and quantity belong here so freight is not treated as a surprise. If the cell will replace an existing press, write current pit, robot rail and utility stubs instead of assuming a greenfield pad.