Who this checklist is for
-
The 9-step checklist
-
1. Write the spec before you call anyone
-
2. Verify where the equipment is actually built
-
3. Ask for material certificates, not "material grade"
-
4. Confirm who owns chemical process equipment design responsibility
-
5. Get the installation scope in writing before you sign
-
6. Confirm spare parts availability before you sign
-
7. Confirm the utilities footprint
-
8. Ask who does commissioning
-
9. Document the handover
-
1. Write the spec before you call anyone
-
Where I still get it wrong
I run purchasing for a 120-person specialty chemicals company. No engineering degree, no process background—just a purchasing folder that got handed to me in 2021 and a lot of very patient engineers who answer my questions. I manage roughly $400,000 a year in chemical process equipment, services, and spare parts across fourteen vendors.
If you're sourcing chemical process equipment and you're not the one who'll actually turn the wrench on it, this checklist is for you. It's the list I run through before I issue any PO—reactor, heat exchanger, pump skid, filter housing, scrubber. Same order, every time.
Nine steps. I'll explain the ones that cost us actual time and money when I skipped them.
Who this checklist is for
This is for the person managing the purchase—not the engineer specifying the process. If you're comparing quotes from a chemical process equipment supplier, coordinating with the chemical process equipment manufacturer, and making sure the chemical process equipment installation doesn't turn into a six-week surprise, this is the checklist that keeps those three conversations aligned.
The engineer will tell you what the equipment needs to do. The checklist makes sure the supplier actually commits to it in writing.
The 9-step checklist
1. Write the spec before you call anyone
This is the step almost everyone skips when they're in a hurry. It's also the cheapest hour you'll spend on the entire project.
If you don't write the spec, the supplier writes it for you—and their spec will be optimized for what they sell, not for what you need. When you source chemical process equipment from multiple manufacturers, you need the same questions asked the same way, or you can't compare the quotes.
My spec sheet has, at minimum: process fluid and concentration, operating temperature and pressure, materials of construction, capacity or throughput, and an interface list (what it connects to upstream and downstream). That last one is the one I forget. Don't forget it.
2. Verify where the equipment is actually built
You'll talk to a chemical process equipment supplier with a nice office, a responsive sales engineer, and a glossy brochure. None of that tells you where the vessel is fabricated or whether the welders are qualified.
Ask for the fabrication address, not the sales address. Then ask for the quality certifications of that specific facility—not the parent company's certifications from a different plant. I've been surprised by how often the two don't match.
3. Ask for material certificates, not "material grade"
"Stainless steel" is not a material specification. Neither is "316."
What you want is the mill certificate: heat number, mechanical properties, chemical composition. For pressure-retaining parts in chemical service, ask for EN 10204 3.1 certificates (or the equivalent your jurisdiction requires). If the supplier can't provide them for the actual heat that goes into your vessel, the cheapest quote suddenly isn't cheap.
I don't have hard data on how often certificates are missing across the industry, but based on our last four equipment buys, it's more common than the sales brochures suggest. Two of the four required follow-up. One required a re-purchase decision.
4. Confirm who owns chemical process equipment design responsibility
If you're buying a standard pump, the manufacturer's design is fine. If you're buying a reactor, a column, or something with a process duty, somebody has to sign off on the process design—not just the mechanical design.
Ask, in writing: "Whose engineer of record stamps the process design?" If the answer is "we'll coordinate with your team," get the specific name and the specific deliverable. This matters because when something doesn't perform to spec after commissioning, that's the first question both sides will ask.
5. Get the installation scope in writing before you sign
This is where chemical process equipment installation goes sideways. "Installation included" can mean four different things:
- Drop-shipped on a truck, you do the rest
- Positioned on the foundation by the supplier's crew, connections by you
- Mechanical install by supplier, electrical and piping by you
- Turnkey—everything, including commissioning
All four get called "installation." Put the scope in the PO line items, not in the proposal PDF. If it's not in the PO, it doesn't exist.
6. Confirm spare parts availability before you sign
This is the step most people skip, and it's the one I now refuse to skip.
Ask for the recommended spare parts list in writing, with lead times and unit prices. Then ask how long the supplier will support that model. A six-week lead time on a $900 mechanical seal is fine—if it's in the budget and on the shelf. A six-month lead time on a gasket is a production outage waiting for a date.
I learned this the hard way. A vendor's gasket quote didn't include the special elastomer we needed—it was made-to-order with an 8-week lead time. We didn't find out until the seal failed.
7. Confirm the utilities footprint
The equipment needs power, cooling water, maybe steam, maybe compressed air, and floor space. Get the utility requirements in writing as a table—voltage, phases, kW, flow rate, pressure, connection size. Then hand it to your facilities team and have them confirm the site can actually supply it.
I've seen a skid arrive and sit for two weeks while electrical ran a new feeder. That's a two-week delay nobody budgeted for.
8. Ask who does commissioning
Commissioning is where every assumption gets tested. Ask:
- Does the supplier send a commissioning engineer, and for how many days?
- Is that included in the price, or is it a separate line item?
- What does the commissioning report include—performance test data, or just "it runs"?
Get the number of days in writing. "Commissioning support included" with no number is a negotiation waiting to happen.
9. Document the handover
Before the final payment, get a handover package: as-built drawings, material certificates, spare parts list, O&M manual, calibration certificates for instruments, and the commissioning report. Confirm the list before you issue the PO, not after.
There's something satisfying about a clean handover folder. I keep ours in a shared drive by equipment tag number. When we have a mechanical issue eighteen months later, having the as-built drawing (i.e., the drawing that reflects what was actually installed, not what was originally designed) saves a service call.
Where I still get it wrong
Even with the checklist, I miss things. The three most common:
- I underestimate the install schedule. The supplier quotes a 14-week lead time and I plan for 14 weeks. Utility work, foundation work, and rigging add weeks the supplier's quote never mentions.
- I forget to ask about a FAT. Factory acceptance testing is a separate conversation from "we test every unit before it ships." Ask if the FAT is witnessed, what it covers, and whether travel is on your side.
- I don't always push back on the spec. When a supplier suggests a simpler material or a different gasket, I used to accept it. Now I forward it to our process engineer with a question: "is this equivalent, or is this cheaper?" Sometimes it's equivalent. Sometimes it's the first sign the supplier is trying to hit a price point.
None of this is complicated. It's just a checklist. But 15 minutes of verification beats three weeks of correction—and I've paid for both, so I know which one I'd rather do again.
A note on timing: this checklist reflects our process as of early 2025. Chemical process equipment sourcing markets shift—lead times, material pricing, and payment terms move. Verify current terms with your supplier before you budget.